|
|
|
A CPT is often used to provide power to metering circuits. Usually by stepping down from a 480V main system to 120V control power.
Option #1: If there is not already an auxiliary compartment in the lineup
1. Add an auxiliary compartment - This is required to mount the CPT + fuses + control power disconnect (CPD)
2. Add metering accessories to the auxiliary compartment
3. Select voltage transformer Note: the factory will size the transformer as required
Option #2: If there is already an auxiliary compartment in the lineup
1. Look in the device modifications tab for a "Control Power Transformer" selection
This article was:

 in a Switchboard/image2019-4-16_13-16-27.png)
 in a Switchboard/image2019-4-16_13-5-47.png)
 in a Switchboard/image2019-4-16_13-9-8.png)