Sandy FAQ

How to configure 150A and 250A Frame 3VA Breakers to P2 and P3 Panels?


This article describes the configuration of configure 150A and 250A Frame 3VA Breakers to P2 and P3 Panels. 

1. Login into COMPAS with valid credentials and create a sales quote or open up an existing sales quote.

2. Then select the add products from the action menu and open up a panelboard configuration.

3. Configure the panel mains as shown below

4. Then configure 3VA61 (150A) or 3VA62 (250A) main breaker as shown below

5. Then configure the 3VA61 (150A) or 3VA62 (250A) branch breakers as shown below.

6. Select 3VA breaker accessories from breaker configuration accessories page as shown below

7. Complete the configuration and add the configuration to quote .

This article was: