This article describes the steps to configure the busing information for the section.

1. Launch the LVS configuration and configure the Switchgear and main/branch as shown below

    

2. Navigate to the "Layout/Design" tab and to the manual layout

3. In the manual layout view, following is noticed as "Section Incomplete"

4. Select the "Section Properties"

5. Configure the relevant properties for busing and power connector as highlighted below.

6. Select the vertical bus amperage

7. On completion the configuration is complete