Leadtime Adjustments on Switchboards and Panelboards - Publish Sandy Articles
Sandy FAQ

Leadtime Adjustments on Switchboards and Panelboards

Current and Expected Future Leadtime Adjustments on Switchboards and Panelboards

[proactively adjusting lead times for all orders not released by May 31st, 2022]

  • SB1 – 32 weeks
  • SB2 – 39 weeks
  • SB3 – 41 weeks
  • P5 – 32 weeks

For clarity these are lead times after release not lead time from order entry. Adjustments are to ensure to meet expectations on delivery. There may be adjustment to  lead times on June 13th with an additional 4-week adjustment outward on switchboards and 2-4 weeks on P2-P5 panelboards. The lead times may not end changing on June 13th, but to provide additional visibility to plan future orders and releases accordingly.

Any orders already released are not affected by this adjustment in lead times.

To view details of the communication, click here