MCC fixes and enhancements in January 2020 release.
- Added WL trip communication PROFINET IO/MODBUS TCP(COM35).
- Added characteristic Expansion Module 2 for PAC4200 meter.
- Removed SmartStart selections.
- Added unit option abbreviations to unit schedule for Surge Suppressor, Starter Type, Fuse Manufacturer, Dual Feeder Unit Barrier.
- Fuse size Other no longer has red conflict and can be configured.
- 400A - 1600A fusible switch no longer has red conflict in punch out.
- Section Nameplate text size 3/8 selections are now allowing character entry for line Engraving4.
- Updated G120 VFD PM240-2 fan sizing calculation to also include unit height instead of sizing based on heat generating components only.
- Standard unit diagram 1 - 4 now show on unit schedule for dual units DFCB, DFDS, DFVNR, DFVC. Dual units DFCB, DFDS are now setting standard unit diagrams on parent level.
- Special unit diagram 2 - 4 now show on unit schedule for dual units DFCB, DFDS, DFVNR, DFVC.
- Dual units with specified control terminal points and viewing window are now only priced once for the left side.
- Common door top wire way is now false for 800/1200A FCB if unit height = 72 and additional unit space is 36.