Current and Expected Future Leadtime Adjustments on Apparatus Products
- Low Voltage Switchgear � 54 Weeks
- Switchboards SB1 � 32 weeks
- Switchboards SB2 � 39 weeks
- Switchboards SB3 � 41 weeks
- Panelboards P2/P3 � 105 days (21 weeks)
- Panelboards P5 � 160 days (32 weeks)
- Busduct � 27 weeks